Community Development Services
Building Standards Services |
|||
Percentage of Full Costs to be Recovered |
Fee |
||
BL-01 |
Building Permit Application – Residential Plan Review |
100% |
$220 plus $52 each 500 sq. ft. or fraction thereof over 1,000 sq. ft. |
BL-02 |
Building Permit Application – Commercial Plan Review |
100% |
$210 first 1,000 sq. ft. plus $130 each add’l 1,000 sq. ft. or fraction thereof (plus costs of outside plan review, if necessary, above cost of normal plan review service.) |
BL-03 |
Minor Building Plan Revision – Commercial |
100% |
$310 |
BL-04 |
Major Building Plan Revision – Commercial |
100% |
$970 |
BL-05 |
Building Inspection – Residential |
100% |
|
BL-06 |
Building Inspection – Commercial |
100% |
|
BL-07 |
Plumbing Plan Review & Inspection |
Residential - $50 application and first fixture, plus $10 each add’l fixture. |
|
BL-08 |
Electrical Plan Review |
100% |
$125/hr (plus cost of outside review when necessary.) |
BL-09 |
Electrical Inspection/Permit - Residential |
100% |
|
BL-10 |
Electrical Inspection/Permit - Commercial |
100% |
|
BL-11 |
HVAC Inspection/Permit - Residential |
100% |
|
BL-12 |
HVAC Inspection/Permit - Commercial |
100% |
|
BL-13 |
Fire Protection System Review |
100% |
(Note 14) $165 |
BL-14 |
Building Plan Revision – Residential |
100% |
$20 Administrative Fee plus fee based on levels of review: |
BL-15 |
Home Improvements |
0 – 1,000 sq. ft. = $50 |
|
BL-16 |
Temporary Structure |
100% |
$70 |
BL-17 |
Gas Line Permit |
100% |
$95 |
BL-18 |
Building Preliminary Plan Review |
0% |
$0 |
BL-19 |
Alternative Building Materials Review |
50% |
$670 |
BL-20 |
Building Demolition Plan Review & Inspection |
100% |
$180 |
BL-21 |
Bldg Relocation Plan Review/Inspection – In City |
100% |
$605 plus costs. |
BL-22 |
Bldg Relocation Plan Review/Inspection – Enter City |
100% |
$605 plus costs. |
BL-23 |
Bldg Relocation Plan Review/Inspection – Leave City |
100% |
|
BL-24 |
Change of Use Permit |
100% |
$250 |
BL-25 |
Conditional Occupancy Inspection |
100% |
$355 /six month period for residential or commercial premises. |
BL-26 |
Building Permit Extension |
100% |
$20 |
BL-27 |
Building Permit Reactivation |
100% |
50% of original permit fee (excluding water and sewer capacity charges.) |
BL-28 |
Special Building Inspection |
100% |
(Note 14) |
BL-29 |
Building Re-inspection Service |
100% |
$135 |
BL-30 |
Contractor Registration |
100% |
$65/year |
BL-31 |
Building Construction Appeal |
$200 (non-refundable) |
|
BL-32 |
Building Standards Appeal |
(Note 21) $0 |
|
BL-33 |
Replacement Building Plans |
100% |
$45 administrative fee, |
BL-34 |
Replacement Building Cards |
100% |
$40 |
BL-35 |
Fence Permit Combined to PL-17 Certificate of Zoning Compliance Review |
|
|
BL-20 |
Building Demolition Plan Review & Inspection |
100% |
$160 |
BL-21 |
Bldg Relocation Plan Review/Inspection – In City |
100% |
$590 plus costs. |
BL-22 |
Bldg Relocation Plan Review/Inspection – Enter City |
100% |
$590 plus costs. |
BL-23 |
Bldg Relocation Plan Review/Inspection – Leave City |
100% |
|
BL-24 |
Change of Use Permit |
100% |
$250 |
BL-25 |
Conditional Occupancy Inspection |
100% |
$330 /six month period for residential or commercial premises. |
BL-26 |
Building Permit Extension |
100% |
$20 |
BL-27 |
Building Permit Reactivation |
100% |
50% of original permit fee (excluding water and sewer capacity charges.) |
BL-28 |
Special Building Inspection |
100% |
(Note 14) |
BL-29 |
Building Re-inspection Service |
100% |
$135 |
BL-30 |
Contractor Registration |
100% |
$60/year |
BL-31 |
Building Construction Appeal |
$200 (non-refundable) |
|
BL-32 |
Building Standards Appeal |
(Note 21) $0 |
|
BL-33 |
Replacement Building Plans |
100% |
$40 administrative fee, |
BL-34 |
Replacement Building Cards |
100% |
$40 |
BL-35 |
Fence Permit |
100% |
$75 – residential. |
BL-05 BUILDING INSPECTION - RESIDENTIAL
Building inspection/permit.- $195 for the first 1,000 sq. ft. or fraction thereof, plus $52 for each add-
itional 500 sq. ft. or fraction thereof. (Note: After hours inspections are charged an additional $120/hr with a three hour minimum.)
Description of Service |
Fee |
Prefabricated fireplace, wood or coal- burning stove. |
$40 |
Shoring permit |
$65 |
Certificate of occupancy. |
$40 |
BL-06 BUILDING INSPECTION – COMMERCIAL
New building and additions thereto including garages and accessory buildings and all other buildings - $220 for the first 1,000 sq. ft. plus $120 per 1,000 sq. ft. of area or fraction thereof. (Note: After hours inspections are charged an additional $120/hr with a three hour minimum.)
Description of Service |
Fee |
|
Alterations permit fees, industrial units, prefabricated assemblies and relocated building permit fees (also includes “walk-through” for interior alterations). Rehabilitation permit fees |
$120 |
for the first 1,000 sq. ft. or fraction thereof, plus $40 for each additional 1,000 sq. ft. |
Rehabilitation of condemned building. |
$105 |
Standard fee plus $80 |
1,000 sq. ft. or fraction thereof, plus |
|
|
Existing buildings. |
$80 |
for the first 1,000 sq. ft. or fraction thereof, |
plus $26 for each additional 1,000 sq. ft.. |
$155 |
|
BL-11 HVAC INSPECTION/PERMIT-RESIDENTIAL
$60 minimum fee for areas up to and including 1,000 sq. ft. plus $30 for each 500 sq. ft. or fraction thereof in excess of 1,000 sq. ft.
BL-09 ELECTRICAL INSPECTION/PERMIT-RESIDENTIAL
Description of Service |
Fee |
|
Temporary service |
$50 |
|
New construction or alterations/additions |
$50 |
minimum fee plus, $20 each additional 500 sq. ft. or fraction thereof over 1,000 sq. ft. |
Low voltage electric (Fire alarms, security systems, coaxial cable, etc.) |
$50 |
minimum fee, plus $10 each 500 sq. ft. or fraction thereof over 1,000 sq. ft. |
BL-12 HVAC INSPECTION/PERMIT-COMMERCIAL
Description of Service |
Fee |
|
New or Additions |
$70 |
minimum fee plus $30 per 1,000 sq. ft. or portion thereof over 1,000 sq. ft. |
Alterations |
$70 |
minimum fee plus $20 per 1,000 sq. ft. or portion thereof over 1,000 sq. ft. |
BL-10 ELECTRICAL INSPECTION/PERMIT-COMMERCIAL
Description of Service |
Fee |
|
Temporary service |
$60 |
(plus 3% State surcharge.) |
New construction or alterations/additions |
$60 |
first 1,000 sq. ft. (minimum fee $60) plus additional $60 per 1,000 sq. ft. up to 50,000 sq. ft., plus $40 per 1,000 sq. ft. from 50,001 sq. ft. to 100,000 sq. ft., plus $30 per 1,000 sq. ft. over 100,001 sq. ft. (plus 3% State surcharge.) |
Low voltage electric (Fire alarms, security systems, coaxial cable, etc.) |
$30 |
minimum fee, plus $20 each 1,000 sq. ft. or fraction thereof over 1,000 sq. ft. (plus 3% State surcharge.) |
Land Use & Long Range Planning Services |
||||
Percentage of Full Costs to be Recovered |
Fee |
|||
PL-01 |
PUD/Concept Plan Review |
50% |
$2,045 |
|
Pl-02 |
PUD/Preliminary Plan Review |
50% |
(per application) |
|
PL-03 |
PUD/Final Development Plan Review |
50% |
$2,775 for 20 acres or less, plus $65 for each additional 5 acres or portion thereof over 20 acres. |
|
PL-04 |
Amended Final Development Plan |
0% |
$0 |
|
PL-05 |
Pre-application Site Plan Review: |
0% |
$0 |
|
PL-06 |
Rezoning Application Review |
100% |
$2,070 SFD on 5 acres or less. |
|
PL-07 |
Corridor Development District Review |
50% |
$680 signage review. $1,455 other. |
|
PL-08 |
Conditional Use Application Review |
50% |
(per application) |
|
PL-09 |
Parking Lot Alteration/Expansion |
100% |
$900 /lot or facility. |
|
PL-10 |
Informal Plan Review |
Note 2 |
$500 |
|
PL-11 |
Preliminary Plat Review |
100% |
$650 for first two |
|
PL-12 |
Final Plat Review |
100% |
$675 for first two lots, $1,750 for first two RDUs |
|
PL-13 |
Lot Split/Minor Subdivision Review |
100% |
$480 – residential. |
|
PL-14 |
Lot Line Adjustment Review |
100% |
$480 – residential. |
|
PL-15 |
Variance Application Review: |
0%
100% |
$0 $100 |
|
PL-16 |
Time Extension Review |
100% |
|
|
PL-17 |
Certificate of Zoning Compliance Review: |
50% |
$60 |
|
PL-18 |
Certificate of Appropriateness |
0% |
$0 |
|
PL-19 |
Sign Plan Review & Inspection – Permanent: |
|
$0 |
|
PL-20 |
Sign Plan Review & Inspection - Temporary |
100% |
$80 |
|
PL-21 |
Sign Plan Review & Inspection - R-O-W |
0% |
$0 |
|
PL-22 |
Annual Permanent Sign Inspection |
0% |
$0 |
|
PL-23 |
Temporary Use Review |
100% |
$70 |
|
PL-24 |
Seasonal Business Review |
100% |
$140-initial appl. $90-renewal fee. |
|
PL-24 A |
Outdoor Seasonal Plant Display/Sales (new) |
100% |
$90 |
|
PL-25 |
Amusement Device Operation Review |
|
$1,000/yr.-Facility license, plus $80 initial filing fee. |
|
PL-26 |
Sexually Oriented Business License |
100% |
$320 |
|
PL-27 |
R-O-W Solicitation Permit |
0% |
$0 |
|
PL-28 |
Peddlers/Solicitation Permit |
100% |
$90/license |
|
PL-29 |
Special Permit Review: |
25% |
$335
|
|
PL-30 |
Home Occupation Permit |
100% |
$90-initial two years |
|
PL-31 |
Wireless Facility Administration Review |
(Note 35) 100% |
New Tower - $2,115 |
|
PL-32 |
Tree Removal Permit |
0% |
$0 |
|
PL-33 |
Block Party Permit |
|
$0-standard permit with use of barricades; |
|
PL-34 |
Garage Sale Permit
Neighborhood Garage Sale Permit (minimum of 10 participating addresses or more) |
|
$5/permit plus $1/sign to a max of 3 signs per address. $3/permit plus $1/sign to a max of 3 signs per address. |
|
PL-35 |
Zoning Inquiry Response: |
(Note 1) 100% |
$160 $0 |
|
PL-36 |
BZA Appeal Processing: |
|
$100 |
|
PL-38 |
City Council Appeal Processing: |
|
$100 |
|
PL-39 |
Planning Pre-Submittal Meeting |
0% |
$0 |
|
PL-40 |
Planning Re-inspection Fee |
100% |
$100 |
|
PL-41 |
Code Enforcement Inspection |
0% |
$0 |
|
PL-43 |
Weed Abatement Service |
|
$350 plus contracted cost of mowing for first mowing of the season. $235 plus contracted cost of mowing for each subsequent mow of the season after the first. |
|
PL-45 |
Annexation Petition Processing |
100% |
$3,700 |
|
PL-46 |
EAZ Development Plan Application Fee |
50% |
$2,405 |
|
PL-47 |
EAZ Administrative Departure Fee |
0% |
$0 |
|
PL-48 |
EAZ Site Plan Approval Fee |
100% |
$2,675 |
|